Brickhills Inclusive Play Area - St Neots TC _001

ID Task Name

Duration

Start

Finish

0712172227010611162126030813182328020712172227020712172227010611162126010611162 nuary 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023

Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program

1 2 3 4 5 6 7 8 9

St Neots - Brickhills (Provisional)

118 days? Fri 13/01/23 Tue 27/06/23 54 days? Fri 13/01/23 Wed 29/03/23 1 day? Fri 13/01/23 Fri 13/01/23 1 day? Mon 23/01/23 Mon 23/01/23 31 days Mon 16/01/23 Mon 27/02/23 1 day? Tue 28/02/23 Tue 28/02/23 19 days Wed 01/03/23 Mon 27/03/23 1 day? Tue 28/03/23 Tue 28/03/23 1 day? Wed 29/03/23 Wed 29/03/23 50 days Thu 30/03/23 Wed 07/06/23 41 days Thu 30/03/23 Thu 25/05/23 50 days Thu 30/03/23 Wed 07/06/23 11 days Tue 13/06/23 Tue 27/06/23 18 days? Thu 08/06/23 Mon 03/07/23 2 days Thu 08/06/23 Fri 09/06/23 1 day Thu 08/06/23 Thu 08/06/23 1 day Fri 09/06/23 Fri 09/06/23 15 days? Thu 08/06/23 Wed 28/06/23 1 day Thu 08/06/23 Thu 08/06/23 7 days Mon 12/06/23 Tue 20/06/23 1 day Wed 21/06/23 Wed 21/06/23 4 days Thu 22/06/23 Tue 27/06/23 1 day? Wed 28/06/23 Wed 28/06/23 3 days Thu 29/06/23 Mon 03/07/23 1 day Thu 29/06/23 Thu 29/06/23 1 day Fri 30/06/23 Fri 30/06/23 1 day Mon 03/07/23 Mon 03/07/23 0 days Mon 03/07/23 Mon 03/07/23

Tender Phase

13/01

Issue tender documents

Site Visit

Tender Response Development

28/02

Tender Submission

Evaluation of submissions Assumed Contract Award Assumed Contract start

28/03 29/03

10 11 17 18 22 23 24 25 26 27 28 29 30 31 32 33 34 35

Planning

Prestart Meetings

Manufacture of Equipment Weekly Progress Meetings

Construction Phase

Site setup

Site Setup - Fencing and compound area

Removal & site preparation

Play Area Installation

Delivery of equipment Installation of Equipment Installation of Fencing Installation of Surfacing

Installation of Turf

Commissioning and Handover

Commissioning

Independent Play Inspection

Snagging

03/07

36 Play Area Handover

Finish-only External Tasks External Milestone Progress

Inactive Milestone Inactive Summary

Task Split

Manual Task Duration-only

Milestone Summary

Brickhills Play Area - St Neots Town Council / 14

Brickhills Play Area - St Neots Town Council / 15

Project: Gantt 1 Date: Fri 24/02/23