Hackleton Play Area Presentation - Hackleton PC_001
ID Task Name
Duration
Start
Finish
12172227010611162126030813182328020712172227020712172227010611162126010611162126310 ary 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 Aug
Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program
1
Hackleton - Hackleton Recreation Ground (Provisional)
125 days? Wed 25/01/23 Tue 18/07/23
2 3 4 5 6 7 8 9
Tender Phase
59 days? Wed 25/01/23 Mon 17/04/23 1 day Wed 25/01/23 Wed 25/01/23 1 day Wed 25/01/23 Wed 25/01/23 31 days Thu 26/01/23 Thu 09/03/23 1 day? Fri 10/03/23 Fri 10/03/23 20 days Mon 13/03/23 Fri 07/04/23 1 day? Mon 10/04/23 Mon 10/04/23 1 day? Mon 17/04/23 Mon 17/04/23 50 days Tue 18/04/23 Mon 26/06/23 41 days Thu 20/04/23 Thu 15/06/23 50 days Tue 18/04/23 Mon 26/06/23 16 days Tue 27/06/23 Tue 18/07/23 17 days Tue 27/06/23 Wed 19/07/23 2 days Tue 27/06/23 Wed 28/06/23 1 day Tue 27/06/23 Tue 27/06/23 1 day Wed 28/06/23 Wed 28/06/23 14 days Tue 27/06/23 Fri 14/07/23 1 day Tue 27/06/23 Tue 27/06/23 8 days Thu 29/06/23 Mon 10/07/23 4 days Tue 11/07/23 Fri 14/07/23 3 days Mon 17/07/23 Wed 19/07/23 1 day Mon 17/07/23 Mon 17/07/23 1 day Tue 18/07/23 Tue 18/07/23 1 day Wed 19/07/23 Wed 19/07/23 0 days Wed 19/07/23 Wed 19/07/23
25/01
Issue tender documents
Site Visit
Tender Response Development
10/03
Tender Submission
Evaluation of submissions Assumed Contract Award Assumed Contract start
10/04
17/04
10 11 17 18 23 24 25 26 27 28 29 30 31 32 33 34
Planning
Prestart Meetings
Manufacture of Equipment Weekly Progress Meetings
Construction Phase
Site setup
Site Setup - Fencing and compound area
Removal & site preparation
Play Area Installation
Delivery of equipment Installation of Equipment Installation of Surfacing
Commissioning and Handover
Commissioning
Independent Play Inspection
Snagging
19/07
35 Play Area Handover
Task Split
Inactive Milestone Inactive Summary
Finish-only External Tasks External Milestone
Milestone Summary Project Summary
Manual Task Duration-only Manual Summary Rollup
Project: Gantt 1 Date: Thu 09/03/23
Hackleton Play Area - Hackleton Parish Council / 16
Hackleton Play Area - Hackleton Parish Council / 17
Progress Deadline