Hinckley and Bosworth Play Area Presentation

ID Task Name

Duration

Start

Finish

121722270106111621260308131823280207121722270207121722270106111621260106111621263 ary 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 A

Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program

1

Hinckley and Bosworth - Burbage Common (Provisional)

120 days Wed 25/01/23 Tue 11/07/23

2 3 4 5 6 7 8 9

Tender Phase

54 days Wed 25/01/23 Mon 10/04/23 1 day Wed 25/01/23 Wed 25/01/23 1 day Wed 25/01/23 Wed 25/01/23 26 days Thu 26/01/23 Thu 02/03/23 1 day Fri 03/03/23 Fri 03/03/23 20 days Mon 06/03/23 Fri 31/03/23 1 day Mon 03/04/23 Mon 03/04/23 1 day Mon 10/04/23 Mon 10/04/23 50 days Tue 11/04/23 Mon 19/06/23 41 days Thu 13/04/23 Thu 08/06/23 50 days Tue 11/04/23 Mon 19/06/23 16 days Tue 20/06/23 Tue 11/07/23 17 days Tue 20/06/23 Wed 12/07/23 3 days Tue 20/06/23 Thu 22/06/23 1 day Tue 20/06/23 Tue 20/06/23 2 days Wed 21/06/23 Thu 22/06/23 14 days Tue 20/06/23 Fri 07/07/23 1 day Tue 20/06/23 Tue 20/06/23 6 days Fri 23/06/23 Fri 30/06/23 3 days Mon 03/07/23 Wed 05/07/23 1 day Thu 06/07/23 Thu 06/07/23 1 day Fri 07/07/23 Fri 07/07/23 3 days Mon 10/07/23 Wed 12/07/23 1 day Mon 10/07/23 Mon 10/07/23 1 day Tue 11/07/23 Tue 11/07/23 1 day Wed 12/07/23 Wed 12/07/23 0 days Wed 12/07/23 Wed 12/07/23

25/01

Issue tender documents

Site Visit

Tender Response Development

03/03

Tender Submission

Evaluation of submissions Assumed Contract Award Assumed Contract start

03/04

10/04

10 11 17 18 23 24 25 26 27 28 29 30 31 32 33 34 35 36

Planning

Prestart Meetings

Manufacture of Equipment Weekly Progress Meetings

Construction Phase

Site setup

Site Setup - Fencing and compound area

Removal & site preparation

Play Area Installation

Delivery of equipment Installation of Equipment Installation of Surfacing Pathway Refurbishment

Turf Re-instatement

Commissioning and Handover

Commissioning

Independent Play Inspection

Snagging

12/07

37 Play Area Handover

Task Split

Inactive Milestone Inactive Summary

Finish-only External Tasks External Milestone

Milestone Summary Project Summary External Tasks External Milestone

Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only

Project: Gantt 1 Date: Thu 02/03/23

Progress Deadline

Burbage Common - Hinckley and Bosworth BC / 24

Burbage Common - Hinckley and Bosworth BC / 25