Laverstock & Ford PC - Sycamore Drive Presentation
ID Task Name
Duration
Start
Finish
1217222701061116212603081318232802071217222702071217222701061116212601061116212631051 ary 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 Augus
1 Laverstock and Ford - Sycamore Drive (Provisional) 128 days? Fri 20/01/23 Tue 18/07/23
Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program
2 3 4 5 6 7 8 9
Tender Phase
62 days? Fri 20/01/23 Mon 17/04/23 1 day Fri 20/01/23 Fri 20/01/23 1 day? Mon 27/02/23 Mon 27/02/23 34 days Mon 23/01/23 Thu 09/03/23 1 day? Fri 10/03/23 Fri 10/03/23 10 days Mon 13/03/23 Fri 24/03/23 1 day? Mon 27/03/23 Mon 27/03/23 1 day? Mon 17/04/23 Mon 17/04/23 50 days Tue 18/04/23 Mon 26/06/23 41 days Thu 20/04/23 Thu 15/06/23 50 days Tue 18/04/23 Mon 26/06/23 16 days Tue 27/06/23 Tue 18/07/23 18 days Tue 27/06/23 Thu 20/07/23 2 days Tue 27/06/23 Wed 28/06/23 1 day Tue 27/06/23 Tue 27/06/23 1 day Wed 28/06/23 Wed 28/06/23 15 days Tue 27/06/23 Mon 17/07/23 1 day Tue 27/06/23 Tue 27/06/23 5 days Thu 29/06/23 Wed 05/07/23 1 day Thu 06/07/23 Thu 06/07/23 3 days Fri 07/07/23 Tue 11/07/23 4 days Wed 12/07/23 Mon 17/07/23 3 days Tue 18/07/23 Thu 20/07/23 1 day Tue 18/07/23 Tue 18/07/23 1 day Wed 19/07/23 Wed 19/07/23 1 day Thu 20/07/23 Thu 20/07/23 0 days Thu 20/07/23 Thu 20/07/23
20/01
Issue tender documents
Site Visit
Tender Response Development
10/03
Tender Submission
Evaluation of submissions Assumed Contract Award Assumed Contract start
27/03
17/04
10 11 17 18 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Planning
Prestart Meetings
Manufacture of Equipment Weekly Progress Meetings
Construction Phase
Site setup
Site Setup - Fencing and compound area
Removal & site preparation
Play Area Installation
Delivery of Equipment Installation of Equipment Installation of Pathway Inastallation of Fencing Installation of Surfacing
Commissioning and Handover
Commissioning
Independent Play Inspection
Snagging
20/07
37 Play Area Handover
Task Split Milestone
Inactive Milestone Inactive Summary Manual Task
Finish-only External Tasks External Milestone
Sycamore Drive - Laverstock And Ford Parish Council / 48
Sycamore Drive - Laverstock And Ford Parish Council / 49
Project: Gantt 1
Made with FlippingBook - Online catalogs