Monks Recreational Play Area

ID Task Name

Duration

Start

Finish

06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 b '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23 Aug '23

1

Lancing PC - Monks Recreation Ground (Provisional)

112 days? Mon 20/02/23 Tue 25/07/23

Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program

2 3 4 5 6 7 8 9

Tender Phase

49 days? Mon 20/02/23 Thu 27/04/23 1 day? Mon 20/02/23 Mon 20/02/23 1 day? Fri 03/03/23 Fri 03/03/23 17 days Tue 21/02/23 Wed 15/03/23 1 day? Thu 16/03/23 Thu 16/03/23 1 day Fri 17/03/23 Fri 17/03/23 3 days Mon 20/03/23 Wed 22/03/23 10 days Mon 27/03/23 Fri 07/04/23 1 day? Thu 20/04/23 Thu 20/04/23 1 day? Thu 27/04/23 Thu 27/04/23 51 days Thu 27/04/23 Thu 06/07/23 51 days Thu 27/04/23 Thu 06/07/23 50 days Fri 28/04/23 Thu 06/07/23 11 days Tue 11/07/23 Tue 25/07/23 16 days Fri 07/07/23 Fri 28/07/23 2 days Fri 07/07/23 Mon 10/07/23 1 day Fri 07/07/23 Fri 07/07/23 1 day Mon 10/07/23 Mon 10/07/23 13 days Fri 07/07/23 Tue 25/07/23 1 day Fri 07/07/23 Fri 07/07/23 5 days Tue 11/07/23 Mon 17/07/23 2 days Tue 18/07/23 Wed 19/07/23 4 days Thu 20/07/23 Tue 25/07/23 3 days Wed 26/07/23 Fri 28/07/23 1 day Wed 26/07/23 Wed 26/07/23 1 day Thu 27/07/23 Thu 27/07/23 1 day Fri 28/07/23 Fri 28/07/23 0 days Fri 28/07/23 Fri 28/07/23

20/02

Issue tender documents

Site Visit

Tender Response Development

16/03

Tender Submission

Initial Evaluation of submissions Shortlisted companies determined

22/03

Public Consultation

20/04

Assumed Contract Award Assumed Contract start

10 11 12 13 20 21 25 26 27 28 29 30 31 32 33 34 35 36 37

27/04

Planning

Prestart Meetings

Manufacture of Equipment Weekly Progress Meetings

Construction Phase

Site setup

Site Setup - Fencing and compound area

Removal & site preparation

Play Area Installation

Delivery of equipment Installation of Equipment

Installation of Fencing and Gates

Installation of Surfacing

Commissioning and Handover

Commissioning

Independent Play Inspection

Snagging

28/07

38 Play Area Handover

Task Split

Inactive Milestone Inactive Summary

Finish-only External Tasks External Milestone

Milestone Summary Project Summary External Tasks External Milestone

Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only

Project: Gantt 1 Date: Wed 15/03/23

Progress Deadline

Page 1

Monks Recreation Ground Play Area - Lancing Parish Council / 18

Monks Recreation Ground Play Area - Lancing Parish Council / 19