Monks Recreational Play Area
ID Task Name
Duration
Start
Finish
06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 b '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23 Aug '23
1
Lancing PC - Monks Recreation Ground (Provisional)
112 days? Mon 20/02/23 Tue 25/07/23
Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program
2 3 4 5 6 7 8 9
Tender Phase
49 days? Mon 20/02/23 Thu 27/04/23 1 day? Mon 20/02/23 Mon 20/02/23 1 day? Fri 03/03/23 Fri 03/03/23 17 days Tue 21/02/23 Wed 15/03/23 1 day? Thu 16/03/23 Thu 16/03/23 1 day Fri 17/03/23 Fri 17/03/23 3 days Mon 20/03/23 Wed 22/03/23 10 days Mon 27/03/23 Fri 07/04/23 1 day? Thu 20/04/23 Thu 20/04/23 1 day? Thu 27/04/23 Thu 27/04/23 51 days Thu 27/04/23 Thu 06/07/23 51 days Thu 27/04/23 Thu 06/07/23 50 days Fri 28/04/23 Thu 06/07/23 11 days Tue 11/07/23 Tue 25/07/23 16 days Fri 07/07/23 Fri 28/07/23 2 days Fri 07/07/23 Mon 10/07/23 1 day Fri 07/07/23 Fri 07/07/23 1 day Mon 10/07/23 Mon 10/07/23 13 days Fri 07/07/23 Tue 25/07/23 1 day Fri 07/07/23 Fri 07/07/23 5 days Tue 11/07/23 Mon 17/07/23 2 days Tue 18/07/23 Wed 19/07/23 4 days Thu 20/07/23 Tue 25/07/23 3 days Wed 26/07/23 Fri 28/07/23 1 day Wed 26/07/23 Wed 26/07/23 1 day Thu 27/07/23 Thu 27/07/23 1 day Fri 28/07/23 Fri 28/07/23 0 days Fri 28/07/23 Fri 28/07/23
20/02
Issue tender documents
Site Visit
Tender Response Development
16/03
Tender Submission
Initial Evaluation of submissions Shortlisted companies determined
22/03
Public Consultation
20/04
Assumed Contract Award Assumed Contract start
10 11 12 13 20 21 25 26 27 28 29 30 31 32 33 34 35 36 37
27/04
Planning
Prestart Meetings
Manufacture of Equipment Weekly Progress Meetings
Construction Phase
Site setup
Site Setup - Fencing and compound area
Removal & site preparation
Play Area Installation
Delivery of equipment Installation of Equipment
Installation of Fencing and Gates
Installation of Surfacing
Commissioning and Handover
Commissioning
Independent Play Inspection
Snagging
28/07
38 Play Area Handover
Task Split
Inactive Milestone Inactive Summary
Finish-only External Tasks External Milestone
Milestone Summary Project Summary External Tasks External Milestone
Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only
Project: Gantt 1 Date: Wed 15/03/23
Progress Deadline
Page 1
Monks Recreation Ground Play Area - Lancing Parish Council / 18
Monks Recreation Ground Play Area - Lancing Parish Council / 19
Made with FlippingBook flipbook maker