Taverham Sandy lane Recreation Ground Presentation
Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program
ID Task Name
Duration
Start
Finish
2603101724310714212805121926020916233006132027061320270310172401081522290512192603101724310 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23 Aug
1
Taverham PC -Sandy Lane New Play Areas and Outdoor Gym (Provisional)
194 days? Thu 13/10/22 Tue 11/07/23
2 3 4 5 6 7 8 9
Tender Phase
102 days? Thu 13/10/22 Fri 03/03/23 1 day? Thu 13/10/22 Thu 13/10/22 1 day? Fri 28/10/22 Fri 28/10/22 48 days Fri 14/10/22 Tue 20/12/22 1 day? Wed 21/12/22 Wed 21/12/22 11 days Thu 22/12/22 Thu 05/01/23 17 days Fri 06/01/23 Mon 30/01/23 1 day? Tue 31/01/23 Tue 31/01/23 5 days Thu 02/02/23 Wed 08/02/23 1 day? Thu 16/02/23 Thu 16/02/23 1 day? Fri 03/03/23 Fri 03/03/23 60 days Mon 06/03/23 Fri 26/05/23 51 days Thu 09/03/23 Thu 18/05/23 60 days Mon 06/03/23 Fri 26/05/23 31 days Tue 30/05/23 Tue 11/07/23 33 days Mon 29/05/23 Wed 12/07/23 4 days Mon 29/05/23 Thu 01/06/23 1 day Mon 29/05/23 Mon 29/05/23 3 days Tue 30/05/23 Thu 01/06/23 30 days Mon 29/05/23 Fri 07/07/23 1 day Mon 29/05/23 Mon 29/05/23 13 days Fri 02/06/23 Tue 20/06/23 3 days Wed 21/06/23 Fri 23/06/23 10 days Mon 26/06/23 Fri 07/07/23 3 days Mon 10/07/23 Wed 12/07/23 1 day Mon 10/07/23 Mon 10/07/23 1 day Tue 11/07/23 Tue 11/07/23 1 day Wed 12/07/23 Wed 12/07/23 0 days Wed 12/07/23 Wed 12/07/23
13/10
Issue tender documents
Site Visit
Tender Response Development
21/12
Tender Submission
Preliminary Evaluation of submissions
Updated design development Second stage submission
31/01
Public Consultation
10 11 12 13 14 21 22 30 31 32 33 34 35 36 37 38 39 40 41 42
16/02
Assumed Contract Award Assumed Order Received
03/03
Planning
Prestart Meetings
Manufacture of Equipment Weekly Progress Meetings
Construction Phase
Site setup
Site Setup - Fencing and compound area
Removal & site preparation
Play Area Installation
Delivery of equipment Installation of Equipment Installation of fencing Installation of Surfacing
Commissioning and Handover
Commissioning
Independent Play Inspection
Snagging
12/07
43 Play Area Handover
Task Split
Inactive Milestone Inactive Summary
Finish-only External Tasks External Milestone
Milestone Summary Project Summary
Manual Task Duration-only Manual Summary Rollup
Project: Gantt 1 Date: Wed 14/12/22
Sandy Lane Recreation Ground - Taverham Parish Council / 86
Sandy Lane Recreation Ground - Taverham Parish Council / 87
Progress Deadline