Taverham Sandy lane Recreation Ground Presentation

Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program

ID Task Name

Duration

Start

Finish

2603101724310714212805121926020916233006132027061320270310172401081522290512192603101724310 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23 Aug

1

Taverham PC -Sandy Lane New Play Areas and Outdoor Gym (Provisional)

194 days? Thu 13/10/22 Tue 11/07/23

2 3 4 5 6 7 8 9

Tender Phase

102 days? Thu 13/10/22 Fri 03/03/23 1 day? Thu 13/10/22 Thu 13/10/22 1 day? Fri 28/10/22 Fri 28/10/22 48 days Fri 14/10/22 Tue 20/12/22 1 day? Wed 21/12/22 Wed 21/12/22 11 days Thu 22/12/22 Thu 05/01/23 17 days Fri 06/01/23 Mon 30/01/23 1 day? Tue 31/01/23 Tue 31/01/23 5 days Thu 02/02/23 Wed 08/02/23 1 day? Thu 16/02/23 Thu 16/02/23 1 day? Fri 03/03/23 Fri 03/03/23 60 days Mon 06/03/23 Fri 26/05/23 51 days Thu 09/03/23 Thu 18/05/23 60 days Mon 06/03/23 Fri 26/05/23 31 days Tue 30/05/23 Tue 11/07/23 33 days Mon 29/05/23 Wed 12/07/23 4 days Mon 29/05/23 Thu 01/06/23 1 day Mon 29/05/23 Mon 29/05/23 3 days Tue 30/05/23 Thu 01/06/23 30 days Mon 29/05/23 Fri 07/07/23 1 day Mon 29/05/23 Mon 29/05/23 13 days Fri 02/06/23 Tue 20/06/23 3 days Wed 21/06/23 Fri 23/06/23 10 days Mon 26/06/23 Fri 07/07/23 3 days Mon 10/07/23 Wed 12/07/23 1 day Mon 10/07/23 Mon 10/07/23 1 day Tue 11/07/23 Tue 11/07/23 1 day Wed 12/07/23 Wed 12/07/23 0 days Wed 12/07/23 Wed 12/07/23

13/10

Issue tender documents

Site Visit

Tender Response Development

21/12

Tender Submission

Preliminary Evaluation of submissions

Updated design development Second stage submission

31/01

Public Consultation

10 11 12 13 14 21 22 30 31 32 33 34 35 36 37 38 39 40 41 42

16/02

Assumed Contract Award Assumed Order Received

03/03

Planning

Prestart Meetings

Manufacture of Equipment Weekly Progress Meetings

Construction Phase

Site setup

Site Setup - Fencing and compound area

Removal & site preparation

Play Area Installation

Delivery of equipment Installation of Equipment Installation of fencing Installation of Surfacing

Commissioning and Handover

Commissioning

Independent Play Inspection

Snagging

12/07

43 Play Area Handover

Task Split

Inactive Milestone Inactive Summary

Finish-only External Tasks External Milestone

Milestone Summary Project Summary

Manual Task Duration-only Manual Summary Rollup

Project: Gantt 1 Date: Wed 14/12/22

Sandy Lane Recreation Ground - Taverham Parish Council / 86

Sandy Lane Recreation Ground - Taverham Parish Council / 87

Progress Deadline

Made with FlippingBook - Online magazine maker