Yate - Kingsgate Play Area Presentation

ID Task Name

Duration

Start

Finish

22270106111621260308131823280207121722270207121722270106111621260106111621263105101 23 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2

Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program

1 2 3 4 5 6 7 8 9

Yate - Kingsgate (Provisional)

124 days? Thu 02/02/23 Tue 25/07/23 42 days? Thu 02/02/23 Fri 31/03/23 1 day? Thu 02/02/23 Thu 02/02/23 1 day? Mon 06/02/23 Mon 06/02/23 17 days Fri 03/02/23 Mon 27/02/23 1 day? Tue 28/02/23 Tue 28/02/23 17 days Wed 01/03/23 Thu 23/03/23 1 day? Fri 24/03/23 Fri 24/03/23 1 day? Fri 31/03/23 Fri 31/03/23 55 days Mon 03/04/23 Fri 16/06/23 51 days Thu 06/04/23 Thu 15/06/23 55 days Mon 03/04/23 Fri 16/06/23 26 days Tue 20/06/23 Tue 25/07/23 28 days Mon 19/06/23 Wed 26/07/23 3 days Mon 19/06/23 Wed 21/06/23 1 day Mon 19/06/23 Mon 19/06/23 2 days Tue 20/06/23 Wed 21/06/23 25 days Mon 19/06/23 Fri 21/07/23 1 day Mon 19/06/23 Mon 19/06/23 15 days Thu 22/06/23 Wed 12/07/23 1 day Thu 13/07/23 Thu 13/07/23 6 days Fri 14/07/23 Fri 21/07/23 3 days Mon 24/07/23 Wed 26/07/23 1 day Mon 24/07/23 Mon 24/07/23 1 day Tue 25/07/23 Tue 25/07/23 1 day Wed 26/07/23 Wed 26/07/23 0 days Wed 26/07/23 Wed 26/07/23

Tender Phase

02/02

Issue tender documents

Site Visit

Tender Response Development

28/02

Tender Submission

Evaluation of submissions Assumed Contract Award Assumed Contract start

24/03

31/03

10 11 18 19 26 27 28 29 30 31 32 33 34 35 36 37 38

Planning

Prestart Meetings

Manufacture of Equipment Weekly Progress Meetings

Construction Phase

Site setup

Site Setup - Fencing and compound area

Removal & site preparation

Play Area Installation

Delivery of equipment Installation of Equipment Installation of Gates Installation of Surfacing

Commissioning and Handover

Commissioning

Independent Play Inspection

Snagging

26/07

39 Play Area Handover

Task Split

Inactive Milestone Inactive Summary

Finish-only External Tasks External Milestone

Milestone Summary Project Summary External Tasks External Milestone

Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only

Project: Gantt 1 Date: Mon 27/02/23

Progress Deadline

Kingsgate Park - Yate Town Council / 42

Kingsgate Park - Yate Town Council / 43

Page 1