Yate - Kingsgate Play Area Presentation
ID Task Name
Duration
Start
Finish
22270106111621260308131823280207121722270207121722270106111621260106111621263105101 23 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2
Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program
1 2 3 4 5 6 7 8 9
Yate - Kingsgate (Provisional)
124 days? Thu 02/02/23 Tue 25/07/23 42 days? Thu 02/02/23 Fri 31/03/23 1 day? Thu 02/02/23 Thu 02/02/23 1 day? Mon 06/02/23 Mon 06/02/23 17 days Fri 03/02/23 Mon 27/02/23 1 day? Tue 28/02/23 Tue 28/02/23 17 days Wed 01/03/23 Thu 23/03/23 1 day? Fri 24/03/23 Fri 24/03/23 1 day? Fri 31/03/23 Fri 31/03/23 55 days Mon 03/04/23 Fri 16/06/23 51 days Thu 06/04/23 Thu 15/06/23 55 days Mon 03/04/23 Fri 16/06/23 26 days Tue 20/06/23 Tue 25/07/23 28 days Mon 19/06/23 Wed 26/07/23 3 days Mon 19/06/23 Wed 21/06/23 1 day Mon 19/06/23 Mon 19/06/23 2 days Tue 20/06/23 Wed 21/06/23 25 days Mon 19/06/23 Fri 21/07/23 1 day Mon 19/06/23 Mon 19/06/23 15 days Thu 22/06/23 Wed 12/07/23 1 day Thu 13/07/23 Thu 13/07/23 6 days Fri 14/07/23 Fri 21/07/23 3 days Mon 24/07/23 Wed 26/07/23 1 day Mon 24/07/23 Mon 24/07/23 1 day Tue 25/07/23 Tue 25/07/23 1 day Wed 26/07/23 Wed 26/07/23 0 days Wed 26/07/23 Wed 26/07/23
Tender Phase
02/02
Issue tender documents
Site Visit
Tender Response Development
28/02
Tender Submission
Evaluation of submissions Assumed Contract Award Assumed Contract start
24/03
31/03
10 11 18 19 26 27 28 29 30 31 32 33 34 35 36 37 38
Planning
Prestart Meetings
Manufacture of Equipment Weekly Progress Meetings
Construction Phase
Site setup
Site Setup - Fencing and compound area
Removal & site preparation
Play Area Installation
Delivery of equipment Installation of Equipment Installation of Gates Installation of Surfacing
Commissioning and Handover
Commissioning
Independent Play Inspection
Snagging
26/07
39 Play Area Handover
Task Split
Inactive Milestone Inactive Summary
Finish-only External Tasks External Milestone
Milestone Summary Project Summary External Tasks External Milestone
Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only
Project: Gantt 1 Date: Mon 27/02/23
Progress Deadline
Kingsgate Park - Yate Town Council / 42
Kingsgate Park - Yate Town Council / 43
Page 1
Made with FlippingBook Annual report maker