arun dc presentation
ID Task Name
Duration
Start
Finish
1722270106111621260308131823280207121722270207121722270106111621260106111621263 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 A
Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program
1 2 3 4 5 6 7 8 9
Arun DC - Aubrey Fletcher (Provisional)
116 days? Tue 31/01/23 Tue 11/07/23 59 days? Tue 31/01/23 Fri 21/04/23 1 day? Tue 31/01/23 Tue 31/01/23 1 day? Fri 17/02/23 Fri 17/02/23 30 days Wed 01/02/23 Tue 14/03/23 1 day? Wed 15/03/23 Wed 15/03/23 21 days Thu 16/03/23 Thu 13/04/23 1 day? Fri 14/04/23 Fri 14/04/23 1 day? Fri 21/04/23 Fri 21/04/23 50 days Mon 24/04/23 Fri 30/06/23 41 days Thu 27/04/23 Thu 22/06/23 50 days Mon 24/04/23 Fri 30/06/23 6 days Tue 04/07/23 Tue 11/07/23 10 days Mon 03/07/23 Fri 14/07/23 2 days Mon 03/07/23 Tue 04/07/23 1 day Mon 03/07/23 Mon 03/07/23 1 day Tue 04/07/23 Tue 04/07/23 7 days Mon 03/07/23 Tue 11/07/23 1 day Mon 03/07/23 Mon 03/07/23 4 days Wed 05/07/23 Mon 10/07/23 1 day Tue 11/07/23 Tue 11/07/23 3 days Wed 12/07/23 Fri 14/07/23 1 day Wed 12/07/23 Wed 12/07/23 1 day Thu 13/07/23 Thu 13/07/23 1 day Fri 14/07/23 Fri 14/07/23 0 days Fri 14/07/23 Fri 14/07/23
Tender Phase
31/01
Issue tender documents
Site Visit
Tender Response Development
15/03
Tender Submission
Evaluation of submissions Assumed Contract Award Assumed Contract start
14/04
21/04
10 11 17 18 21 22 23 24 25 26 27 28 29 30 31 32
Planning
Prestart Meetings
Manufacture of Equipment Weekly Progress Meetings
Construction Phase
Site setup
Site Setup - Fencing and compound area
Removal & site preparation
Play Area Installation
Delivery of equipment Installation of Equipment Installation of Surfacing
Commissioning and Handover
Commissioning
Independent Play Inspection
Snagging
14/07
33 Play Area Handover
Finish-only External Tasks External Milestone
Inactive Milestone Inactive Summary
Task Split
Manual Task Duration-only Manual Summary Rollup
Milestone Summary Project Summary
Project: Gantt 1 Date: Tue 14/03/23
Aubrey Fletcher Play Area- Arun District Council / 12
Aubrey Fletcher Play Area- Arun District Council / 13
Progress Deadline
Made with FlippingBook - Online Brochure Maker