arun dc presentation

ID Task Name

Duration

Start

Finish

1722270106111621260308131823280207121722270207121722270106111621260106111621263 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 A

Provisional Time Line We have created a Preliminary Tender Programme to illustrate the timeline associated with the project. All phases are shown as a black line with the constituent sub items below in orange. They are arranged in the order that they will occur and are shown with their start and finish dates. Tender Program

1 2 3 4 5 6 7 8 9

Arun DC - Aubrey Fletcher (Provisional)

116 days? Tue 31/01/23 Tue 11/07/23 59 days? Tue 31/01/23 Fri 21/04/23 1 day? Tue 31/01/23 Tue 31/01/23 1 day? Fri 17/02/23 Fri 17/02/23 30 days Wed 01/02/23 Tue 14/03/23 1 day? Wed 15/03/23 Wed 15/03/23 21 days Thu 16/03/23 Thu 13/04/23 1 day? Fri 14/04/23 Fri 14/04/23 1 day? Fri 21/04/23 Fri 21/04/23 50 days Mon 24/04/23 Fri 30/06/23 41 days Thu 27/04/23 Thu 22/06/23 50 days Mon 24/04/23 Fri 30/06/23 6 days Tue 04/07/23 Tue 11/07/23 10 days Mon 03/07/23 Fri 14/07/23 2 days Mon 03/07/23 Tue 04/07/23 1 day Mon 03/07/23 Mon 03/07/23 1 day Tue 04/07/23 Tue 04/07/23 7 days Mon 03/07/23 Tue 11/07/23 1 day Mon 03/07/23 Mon 03/07/23 4 days Wed 05/07/23 Mon 10/07/23 1 day Tue 11/07/23 Tue 11/07/23 3 days Wed 12/07/23 Fri 14/07/23 1 day Wed 12/07/23 Wed 12/07/23 1 day Thu 13/07/23 Thu 13/07/23 1 day Fri 14/07/23 Fri 14/07/23 0 days Fri 14/07/23 Fri 14/07/23

Tender Phase

31/01

Issue tender documents

Site Visit

Tender Response Development

15/03

Tender Submission

Evaluation of submissions Assumed Contract Award Assumed Contract start

14/04

21/04

10 11 17 18 21 22 23 24 25 26 27 28 29 30 31 32

Planning

Prestart Meetings

Manufacture of Equipment Weekly Progress Meetings

Construction Phase

Site setup

Site Setup - Fencing and compound area

Removal & site preparation

Play Area Installation

Delivery of equipment Installation of Equipment Installation of Surfacing

Commissioning and Handover

Commissioning

Independent Play Inspection

Snagging

14/07

33 Play Area Handover

Finish-only External Tasks External Milestone

Inactive Milestone Inactive Summary

Task Split

Manual Task Duration-only Manual Summary Rollup

Milestone Summary Project Summary

Project: Gantt 1 Date: Tue 14/03/23

Aubrey Fletcher Play Area- Arun District Council / 12

Aubrey Fletcher Play Area- Arun District Council / 13

Progress Deadline